Timeline

Event Date
Environmental Review Jan. 2003 - Dec. 2004
Final Environmental Impact Report published Mar. 2004
Intake Facility Design and Engineering Jan. 2005 - Jun. 2006
Pipelines Design and Engineering Jan. 2005 - Aug. 2007
Mitigated Negative Declaration completed Mar. 2006
Intake Facility Construction Dec. 2006 - Dec. 2009
Intake Facility Groundbreaking Ceremony May 7, 2007
Pipeline Segment 2 Jul. 2007 - Jul. 2009
Pipeline Segment 1 Aug. 2007 - May 2009
Clay Station Pumping Plant Fall 2007 - Spring 2009
Camanche Station Pumping Plant Fall 2007 - Spring 2009
Northern Reach Pipeline Fall 2007 - Fall 2009
Middle Reach Pipeline Fall 2007 - Fall 2009
Southern Reach Pipeline Fall 2007 - Fall 2009
Brandt Flow Splitting Facility Fall 2007 - Fall 2009
Pipeline Segment 3 Oct. 2007 - May 2009
Pipeline Segment 4 Jan. 2008 - Apr. 2009